This update was released earlier in the month, we are just getting around to posting it now though, oops!
An aerial view of the Intermodal project.
The Intermodal Facility is 78% complete and on schedule for opening in Fall 2010. Framing, painting, and other finish work is now the focus as well as final permitting inspections.
Terminal End Improvements (TEI)

Skywalk

Customer Service Operations Building (CSO)

Garage

I’ve been assured that the garage will include bicycle parking. Covered bike parking is always a good thing… RI’s next train station after this, Wickford Junction, is also designed with covered bike parking.