The Intermodal Facility is 85% complete and on schedule for opening in Fall 2010. The project has officially been renamed the InterLink, a name demonstrative of its multi-modal connectivity. Students attending Rhode Island Colleges and Universities with concentrations in business, marketing and/or communications were invited to assist in branding the facility by submitting names and taglines for consideration.
The winning proposal was submitted by Bryant University seniors Justin Andrews. Jameson (Jack) Antonowicz, Jacquelyn Parr, Pat Sargent and Brittany Beckerman with help from Mara Chapin and Hillary Smith. The students are all marketing majors under the instruction of Professor Jean Murray. The final name, tagline and logo was a collaborative effort of RIAC working in conjunction with their agency of record, RDW Group. (Name, logo and tag are visible above.)
Terminal End Improvements (TEI)
At the terminal end, drywall installation on ceilings and walls is complete. Painting and finish work is now underway. The elevator install is complete and awaiting final inspection. Framework is being installed under the escalators. The two moving walkways in the TEI are nearing completion.Metal panel and light fixture installation is complete for the TEI ceiling. Metal parapet framing and sun shades have been set in place along the exterior of the curtain wall glass.
Skywalk
Moving walkway work continues with the addition of chains, glass outer rails and rubber handrails at various points in the Skywalk. Lighting fixtures are complete. Framing for smoke doors is complete. Work on fire alarms, communication wiring and lighting control systems are all ongoing. Another milestone has been reached- the stretch fabric ceiling installation is underway. The fabric is heated by a propane powered unit and stretched into place. Once the fabric has reached a certain elasticity the installed can wedge the sides into the already installed frame.
Customer Service Operations Building (CSO)
Exterior door and hardware installation are complete. Painting is underway as well as installation of lighting fixtures. All testing and programming for cooling tower and other control systems have been continuing. For tenant work, application of prime paint on finished drywall is finished. Metal panels are being installed simultaneously to rough-in for overhead systems. Major accessories in the toilet room have been installed and toilet partitions are to being placed next month. Glass doors between the CSO and garage connector bridge have been installed. Site work at the north side of CSO has started. Once the office trailers are removed from the site, the roadway, sidewalks and curb can be constructed.
Garage
Granite curbing and concrete sidewalk are being installed on Jefferson Boulevard and other locations surrounding garage. Detail work is on going throughout the garage. Lights were installed at the south ramp entrance canopy meaning the majority of permanent light is up and running inside the garage. Elevators are at various stages of completion. Concrete slabs have been poured for stairs. Escalators are in the process of being assembled. An anti-projectile screen has been installed facing the train tracks. Work on the parking revenue equipment has begun. Installation of fire alarms and lighting controls continue throughout the garage. Fueling tanks and windshield washer fluid tanks are installed. Fit out for fueling islands and carwash equipment in reclamation room has been on going. Installation of the fueling system at the platforms continues. Rental car quick turn around office construction is well underway in the garage.