ProJo: Long-awaited pedestrian bridge taking shape over Providence River

Photo from RIDOT’s Facebook page

The bridge is expected to be completed by the end of October 2018, said Charles St. Martin, spokesman for the state Department of Transportation, the agency in charge of the $16.97-million project.

[…]

The pedestrian bridge now being built on the piers that once carried the highway will eventually connect a nearly 5-acre park on the west side of the river with a nearly 2-acre park to its east. The DOT is responsible for constructing the bridge and parks, among the final elements of the highway realignment.

[…]

The DOT expects to put parks construction out to bid by the end of this year, start work in the spring and conclude the work by summer 2019, St. Martin said.

The new bridge will a key link in the CityWalk project currently under development.

2

I-195 Redevelopment District Commission Meeting – November 15, 2017

Rendering of Kendall Hotel Group’s proposal for Parcel 1A along the Providence River.

A meeting of the I-195 Redevelopment District Commission will be held at Rhode Island Commerce Corporation, 315 Iron Horse Way, Suite 101, Providence, Rhode Island, on Wednesday, November 15, 2017, beginning at 5:00 P.M., for the following purposes:

I. Public Session195-round

  1. Welcoming remarks by Chairperson Davis.
  2. Approval of the Minutes of the Commission meeting held on October 16, 2017.
  3. Executive Director’s Report.
  4. Update and discussion on the proposed development by Waldorf Capital Management on Parcel 30; Vote to consider a reduction in the purchase price for Parcel 30.*
  5. Commission discussion on the possible use of park parcels for ancillary uses such as a visitor’s center and sculpture garden.
  6. Discussion of proposed 2018 Commission meeting schedule.
  7. Vote to ratify the approval of a Level 1 application as submitted by the Kendall Hotel Group for the proposed hotel development on Parcel 1A.*
  8. Chairperson’s Report/Agenda for next meeting on Wednesday, December 11, 2017 at 5:00 P.M.
  9. Vote to Adjourn.

*To the extent then complete, proposed resolutions under agenda items 4 and 7 will be posted on the Commission’s website www.195district.com at 12pm on November 15th.

1

I-195 Redevelopment District Commission Meeting – August 15, 2016

A meeting of the I-195 Redevelopment District Commission will be held at Rhode Island Commerce Corporation, 315 Iron Horse Way, Suite 101, Providence, Rhode Island, on MONDAY, AUGUST 15, 2016, beginning at 3:00 P.M., for the following purposes:

195-roundI. Public Session

  1. Welcoming Remarks by Chairperson Joseph Azrack.
  2. Approval of the Minutes of the Commission Meetings Held on June 20, 2016.
  3. Executive Director’s Report.
  4. Report on status of District’s financial audit by Lisa Lasky, RI Commerce Corporation Chief Financial Officer.
  5. Discussion and Vote regarding proposed allocation of funds to pedestrian bridge construction budget.
  6. Presentation and discussion regarding District land use planning.
  7. II. Executive Session

    To consider and act upon such matters as may be considered at a meeting closed to the public pursuant to Rhode Island General Laws, Section 42-46-5(a) (the Open Meetings Law), specifically matters permitted to be so considered under (i) subsection (5) (disposition of public property).

  8. Review of Status of Proposals to Purchase and Develop District Property.
  9. III. Public Session

  10. Chairperson’s Report/Agenda for next meeting on September 19, 2016 at 5:00 P.M.
  11. Vote to Adjourn.
0

ProJo: Pedestrian bridge moving forward in Providence

providence-river-pedestrian-bridge-001

The fate of a long-delayed pedestrian bridge across the Providence River is back on track, after a flurry in recent weeks of negotiations, meetings and budget deliberations.

The Department of Transportation expects to award a bid in October so the bridge can be completed by November 2018, spokeswoman Lisbeth Pettengill told The Providence Journal.

The DOT and the I-195 Redevelopment District Commission are pledging to spend about $6 million more than the DOT’s earlier estimate to build the bridge.

0

Providence Bicycle and Pedestrian Advisory Commission Meeting – June 15, 2016

Providence Bicycle and Pedestrian Advisory Commission
June 15, 2016, 4:45 PM
Doorley Municipal Building
444 Westminster Street, First Floor
Providence, RI 02903

bpac-roundAgenda

  1. Roll Call
  2. Approval of May Meeting Minutes (For Action)
  3. Francis Street Modifications – Downtown (For Action) – Providence Place Mall intends to make improvements to the Francis Street side of the mall, including the sidewalk area and street. DPW seeks comment from the BPAC regarding the plans.
  4. Harris Avenue Modifications – Smith Hill, Valley, Olneyville (For Action) – The Department of Public Works has proposed striping for Harris Avenue. DPW seeks comment from the BPAC regarding the conceptual plans.
  5. Potential Bicycle Improvements through Downtown to improve access to Classical High School – Downtown (For Discussion)
  6. Potential Bicycle and Pedestrian Improvements to streets surrounding the new LINK District waterfront parks and Providence River Pedestrian Bridge – Downtown, Fox Point (For Discussion)
  7. Announcements and Staff Updates (For Discussion)
  8. Adjournment
Full Disclosure: I am a member of this Commission.
0

Building Bridges: The Launch – May 28, 2016

building-bridges

From Facebook:


Join us for food & drink by MATUNUCK OYSTER BAR, live music by headliners MARK CUTLER & MEN OF GREAT COURAGE, THE NELSONIANS, and THE RED PENNYS, and kick off summer in style at THE LAUNCH! Then wander upriver to enjoy an evening of WATERFIRE!

Building Bridges is a new movement to activate, celebrate, imagine, and help realize Providence’s future premiere riverfront park and its pedestrian bridge, and THE LAUNCH! is our exciting first event. Together, we can show what an amazing, vibrant public space this can be, and why building our park and bridge is so important!

A ticket gets you a beverage and admission for a day of great food, live music, and celebration. Children under 12 free. This is a rain or shine event!

Tickets available via Eventbrite
0

Providence Bicycle and Pedestrian Advisory Commission Meeting – May 18, 2016

Providence Bicycle and Pedestrian Advisory Commission Meeting
Wednesday, May 18, 2016, 4:45 PM
Joseph Doorley Municipal Building, 1st Floor Meeting Room
444 Westminster Street, Providence, RI 02903

bpac-roundAgenda

  1. Roll Call
  2. Approval of April Meeting Minutes (For Action)
  3. Waterman Street Modifications – Wayland (For Action) – The City of Providence intends to restripe Waterman Street between Butler Avenue and the Henderson Bridge. This restriping will include the relocation of on street parking from the south side to the north side of Waterman and installation a crosswalk near the ramp to the Henderson Bridge. DPW seeks comment from the BPAC regarding the preliminary plans.
  4. Eddy Street Restriping – Upper South Providence (For Action) – The Rhode Island Department of Transportation intends to restripe Eddy Street from Willard Avenue north to the I-95 Eddy Street underpass. RIDOT’s restriping plan includes bike lanes along portions of Eddy Street in both directions. DPW seeks comment from the BPAC regarding RIDOT’s preliminary striping plans.
  5. Bicycle Infrastructure Improvements to Connect to New Waterfront Parks and Pedestrian Bridge – Downtown and Fox Point (For Action) – The Rhode Island Department of Transportation will soon begin construction on the Providence River Pedestrian Bridge and two new waterfront parks to be placed on the former I-195 land on either side of the Providence River. DPD seeks ideas from the BPAC regarding new bicycle infrastructure to improve access from Downtown and Fox Point to the new parks and bridge.
  6. DPW Report on Status and Outcomes of Autotmatic Pedestrian Signal Pilot Project (For Discussion)
  7. Announcements and Staff Updates (For Discussion)
  8. Adjournment
Full Disclosure: I am a member of this commission.
2

PBN: RIDOT moves up Providence River pedestrian bridge schedule

providence-river-pedestrian-bridge-001

Rendering of the planned Providence River Pedestrian Bridge

The process for building a pedestrian bridge connecting the two sides of the Providence River in the I-195 redevelopment district, will move forward this month, the R.I. Department of Transportation announced Tuesday.

[…]

The construction schedule, described in a recent reporting by the DOT, would have preliminary work beginning in the fall. Construction of the $13.2 million bridge project is expected to span two seasons, with completion anticipated in early 2018.


Yay!

2

WPRI: Downtown parks, pedestrian bridge on track after setbacks

providence-river-pedestrian-bridge-001

Plans to build two public parks and a pedestrian bridge in downtown Providence have resumed now that a proposal for a waterfront baseball stadium has fallen through.

State and city officials say they’re refocusing on developing the land, which was cleared after Interstate 195 was relocated. The project, which includes building a pedestrian bridge across the Providence River with a park on each side, has faced several setbacks.

On again, off again, on again…

3

News on the Providence River Pedestrian Bridge

providence-river-pedestrian-bridge-001

The Providence Journal: Pedestrian bridge over Providence River being ‘reevaluated’ by RI transportation officials

The Rhode Island Department of Transportation is now “reevaluating” the bridge project, RIDOT Director Peter Alviti Jr. said in a statement in response to questions from The Providence Journal.

“Given our current funding levels, RIDOT is reevaluating this project given the availability of funding,” Alviti wrote. “RIDOT must take into consideration the many needs for Rhode Island’s deficient bridges and deteriorated roadways. With reliable, predictable funding provided through the RhodeWorks program, RIDOT would be in a better position to schedule and fund projects such as the pedestrian bridge.”

The Feds let us use the money we’d save on not removing the piers in the river on the new highway. Will the Feds make us remove the piers if we don’t build the bridge?

Salisbury said his association would be “really disappointed” if the bridge isn’t built — plus, he questions what would happen to the old highway piers that once carried Route 195 over the river and now remain in the river, intended to carry the pedestrian bridge along the highway’s old path. Seven years ago, the DOT agreed to build the pedestrian bridge on those piers — and said the $2 million it would save by not demolishing them would go toward building the bridge. The DOT has already paid $1.4 million to design the pedestrian bridge, which was expected to cost $5.5 million.


Also, last week, PBN reported on possible changes to the design of the bridge.

Continue Reading →

16

I-195 Redevelopment District Commission Parks Design Subcommittee – December 1, 2014

A meeting of the I-195 Redevelopment District Commission Parks Design Subcommittee will be held at Rhode Island Commerce Corporation, 315 Iron Horse Way, Providence, Rhode Island, on MONDAY, DECEMBER 1, 2014, beginning at 4:45pm for the following purposes:

195-roundPublic Session

I-195 Redevelopment Commission: Commissioners John Kelly, Barbara Hunger, Diana Johnson Jan Brodie, Executive Director
Department of Transportation: Lambri Zerva
Architects and Engineers: David Freeman, CDR Maguire
Nina Brown, Brown Richardson Rowe (?) Kelly Carr, BETA (?)

Call to Order

  1. Discussion regarding bridge height and other suggestions relative to River activation, views and pathways – Director Lewis’s letter
  2. Discussion concerning other design issues impacted by item 1, including water feature, river edge terracing.
  3. Other matters that still need resolution before DOT/Designers can proceed beyond 30%.
  4. Vote to Adjourn.
0

PBN: Would dredging return bustle to riverfront?

Last dredged in the 1990s, the river is now so shallow in places that even the Proud Mary has to dance around obstructions and can’t reach Waterplace Park at low tide. “I know where all those difficult places are, but north of Point Street you can run aground virtually any time,” McGinn said. “I just have to be careful and cannot go into Waterplace Park basin when it’s real low.”

Preventing the river from filling in with natural sediment requires periodic dredging, something neither the city nor state has been eager to finance in recent years. The federal government declined to tap a pool of funds set aside for dredging projects that maintain cargo shipping channels.

As a result, much of the center and eastern side of the river is too shallow for boats even at midtide and the WaterFire lightings must be planned around tidal schedules and closures of the hurricane barrier to keep water inside.

Now the depth of the river and role marine traffic should play in the revitalization of downtown has become a discussion point again as the state begins construction of new public spaces on the former Interstate 195 land.


What if traffic in the Woonasquatucket looked like this?:

“Amsterdam Canals: It’s busy on the Prinsengracht” © Peter Eijking

Continue Reading →

2

PBN: Long-planned pedestrian bridge closer to reality

providence-river-pedestrian-bridge-original-design

The original winning design scheme for the Providence River Bridge.

The first permanent structure to rise from Providence’s Interstate 195 lands almost certainly won’t be a new office or apartment building, but the long-planned pedestrian bridge crossing the Providence River.

After four years of planning, the 330-foot-long arc connecting new parks planned for both sides of the river is now nearly ready for bids from construction contractors.

[…]

“We are at 30 percent design and on schedule for the project to be bid out by the end of this year,” Bonnie Nickerson, Providence director of long-range planning, said last week. “The details being worked out now are very technical, such as levels of lighting. The structural elements and design decisions have been made and those are solid.”

The Providence Planning Department is having a public informational meeting about the bridge today (Sept. 29th) at 5pm.
4

195 Redevelopment District Commission Meeting – September 15, 2014

A meeting of the I-195 Redevelopment District Commission will be held at Rhode Island Commerce Corporation, 315 Iron Horse Way, Providence, Rhode Island, on MONDAY, September 15, 2014, beginning at 5 P.M., for the following purposes

195-roundI. Public Session

  1. Welcome by Chairperson: Chairperson Colin Kane.
  2. Approval of the Minutes of the Commission Meetings Held on August 18, 2014.
  3. Executive Director’s Report – Review of Activities During Past Month and Business Plan for the Period September – December 2014.
  4. Presentation of District Audit by LGCD, District Auditor, and Vote Regarding Acceptance of Audit.
  5. Update from Jones Lang LaSalle on Market Conditions and Strategies for October 15, 2014 RFI Submission Date.
  6. Update from DOT Director Lewis on Work Progress on I-195 Surplus Land.
  7. Discussion and Review of Draft Parks Maintenance and Management Budget.
  8. Discussion and Vote on Allocation of Funds from the EPA Grant to the District.
  9. Update from Counsel Regarding District Permitting Process and Legal Issues Subcommittee.
  10. II. Executive Session

    To consider and act upon such matters as may be considered at a meeting closed to the public pursuant to Rhode Island General Laws, Section 42-46-5(a) (the Open Meetings Law), specifically matters permitted to be so considered under subsection (5) (acquisition and disposition of public property).

  11. Review of Status of Proposals to Purchase and Develop District Property.
  12. III. Public Session

  13. Chairman’s Report – Review of Activities in Past Month and Proposed Future Activities/ Tentative Agenda for October 20, 2014 Meeting.
  14. Vote to Adjourn.
0

I-195 Redevelopment District Commission – Parks Design Subcommittee Meeting – September 12, 2014

A meeting of the I-195 Redevelopment District Commission – Parks Design Subcommittee will be held at Rhode Island Commerce Corporation, 315 Iron Horse Way, Providence, Rhode Island, on Friday, September 12, 2014, beginning at 1:30 P.M., for the following purposes
The time for this meeting has been changed to 2:30pm

195-roundPublic Session

  • I-195 Redevelopment Commission: Commissioners Barbara Hunger, John Kelly, Diana Johnson
  • Jan Brodie, Executive Director
  • Department of Transportation: Lambri Zerva
  • Architects and Engineers: David Freeman, CDR Maguire

Call to Order

  1. Approval of the Minutes of the Parks Design Subcommittee Meeting held on August 19, 2014.
  2. West Side Park: Pavilion – Bathrooms – separate or within single structure, number
    – Further discussion concerning storage and concession
    – Write up a Program of Uses
    – Discussion of contracting for additional scope for alternate designs
  3. Response to Public Comment from August 19, 2014 meeting, including water access
  4. Connections to CityWALK, bicycle lanes, WaterFire, River Walk in connection with South Street Landing
  5. Vote to Adjourn.
0

195 Redevelopment District Commission Meetings – August 18, 19, & 20, 2014

A meeting of the I-195 Redevelopment District Commission will be held at Rhode Island Commerce Corporation, 315 Iron Horse Way, Providence, Rhode Island, on MONDAY, AUGUST 18, 2014, beginning at 5:00pm, for the following purposes

195-roundI. Public Session

  1. Welcome by Chairperson: Chairperson Colin Kane.
  2. Approval of the Minutes of the Commission Meeting Held on July 21, 2014.
  3. Executive Director’s Report – Review of Activities During Past Month and Business Plan for the Period August – December 2014.
  4. Update Regarding the Request by Mr. Stephen Beranbaum for Use of a Portion of Parcel 28 for Parking and Vote.
  5. Update from Counsel Regarding District Permitting Process; Discussion Regarding Creation of Legal Issues Subcommittee; Vote Regarding Creation of Legal Issues Subcommittee and Designation of Members.
  6. II. Executive Session

    To consider and act upon such matters as may be considered at a meeting closed to the public pursuant to Rhode Island General Laws, Section 4264665(a) (the Open Meetings Law), specifically matters permitted to be so considered under subsection (5) (acquisition and disposition of public property).

  7. Review of Proposals to Purchase and Develop District Property; Vote to Proceed with/Reject Proposals.
  8. III. Public Session

  9. Chairman’s Report – Review of Activities in Past Month and Proposed Future Activities/ Tentative Agenda for September 15, 2014 Meeting.
  10. Vote to Adjourn.

Continue Reading →

1